Claim-to-outcome ledger
Proposed expansion
450,000 square feet, contemplated CoreWeave 20-year lease and 180 MW requirement.
Council minutes explicitly describe a final NIPSCO power agreement as gating. They describe the contemplated lease but do not prove that its execution was a development-agreement precondition. Hammond later said unspecified milestones remained unsatisfied after two extensions and the agreement expired.
Community payments
Up to $4 million each year for 20 years.
Council minutes describe up to $80 million intended for College Bound. The reviewed record does not show the expansion activated, a payment trigger occurring, or a payment missed.
Additional $25 million
Lump-sum concept discussed during extension.
In December 2025, officials said the payment was still being finalized and was not in the agreement. It must not be added to an enforceable-benefit total.
Jobs and incentives
35–90 permanent jobs; construction jobs; 10-year construction abatement; 20-year technology deduction.
These projected benefits and contemplated tax terms related to the unactivated expansion. Claimed incentives, job creation and foregone-revenue amounts have not been established.
Power agreement
Final NIPSCO agreement identified as the last major step.
The public minutes repeatedly describe utility negotiations as a gating condition. The executed tariff, infrastructure scope and cost allocation were not located in the reviewed packet.
Existing DX-1
Operator publishes 105,000 square feet and up to 20 MW.
The expired CoreWeave agreement concerned a new building. Digital Crossroad still markets DX-1 as an operating Hammond facility. Its “up to 20 MW” figure is not assumed to mean critical IT load.
What changed
Council approves the development agreement
The power agreement is explicitly described as gating. A 20-year CoreWeave lease is contemplated, but its execution is not identified in the minutes as a contractual precondition.
First extension discussed and approved
Utility negotiations continue. A separate $25 million payment is discussed but is not yet in the agreement.
Extended deadline passes
After two extensions, required obligations and milestones remain unsatisfied. The city does not name the exact failed milestones.
City announces expiration
Hammond says it will grant no further extension. The existing facility is unaffected.
Source packet
- Hammond Common Council minutes — 9 Jun 2025 →Primary municipal PDF · pp. 3–4 · proposal, lease, jobs, tax terms, community payment and power contingency
- Hammond Common Council minutes — 22 Dec 2025 →Primary municipal PDF · pp. 1–2 and resolution at p. 10 · extension, power negotiations and noncontractual $25M discussion
- City of Hammond — expiration notice →Primary municipal outcome record · 1 Jul 2026
- Digital Crossroad — existing DX-1 facility →Operator source · current facility status, published area and capacity
- Machine-readable claim ledger →DataCenterData normalization · version 0.2
- Classification methodology →Why an unsatisfied precondition is not automatically a missed payment